SCOPE OF WORK
2 x gas furnace boilers with pipe insulation
3 x rooftop split HVAC units
Economizers and demand controls
LED relamp and reballasting
Brand new LED lighting in the gym
COST BREAKDOWN
Total Project Cost: $944,495
Incentives Secured: $370,000
Customer Cost: $574,495
ENERGY SAVINGS (ANNUALLY)
195,163.21 kwH
6,650.93 therms
176 Metric Tons CO2 Reduced
While students were enjoying their summer break, the team at Donnelly Energy was hard at work completing a Direct Install upgrade at the West Long branch School District. We’re talking about the works: lighting, HVAC, and new boilers. This project had it all and we finished right before the start of the 2023-2024 school year.
As the school had already started making the switch to LEDs, we came in to finish off any remaining fluorescent and incandescent lamps with a quick relamp/reballast upgrade. The big lighting star of this project was the work we did in the gymnasium, where we installed brand-new LED high bays.
FUN FACT
The carbon emissions this project reduces are equal to offsetting the carbon footprint of energy use for 22.2 homes.
DIRECT INSTALL FROM JCP&L
Jersey Central Power & Light (JCP&L)’s Direct Install (DI) Program makes upgrading your business with energy-saving equipment easy and affordable. You can save on monthly energy costs with available energy-efficient lighting, HVAC, and refrigeration upgrades. Best of all, the program offers upgrades at no out-of-pocket cost to you by providing significant incentives and 0% financing for up to 5 years.